Cd. Juárez, Chihuahua, Mexico

Wastewater Collection and Treatment Project for Tres Jacales, Chihuahua

Status: Completed Construction

Background

In 2010, the communities of El Millón, Tres Jacales and Jesus Carranza did not have wastewater collection and treatment systems. The population used latrines and septic tanks, the lack of wastewater collection and treatment in the project area resulted in untreated wastewater runoffs, which created a risk for transmission of diseases due to the potential for human contact with unhealthy waters and soil contamination. The untreated discharges had a potential to reach surface and/or groundwater.

Description

The purpose of this project is to eliminate exposure to untreated wastewater produced by El Millón, Tres Jacales and Jesus Carranza by the introduction of sanitary services in these communities, contributing to the reduction of water pollution and the risk of water-borne diseases.

Benefits

The project consists of the construction of the wastewater collection systems in the three localities and the construction of a 0.13 mgd wastewater treatment plant in El Millón to serve the three communities. The design of this regional plant includes the construction of an anaerobic lagoon, a secondary lagoon and a polishing pond, in addition to a sewage pump station and a pressurized conveyance line.

Project Financing

Total Project Cost US 3.1M
NADB Funding US 1M - NADB Grant: BEIF
Other Funding Partners CONAGUA
Project Sponsor (JCAS - JRAS)

Results Measurement

Results are measured upon completion of the project through a closeout process that assesses project performance within 6-12 months after completion, as well as the achievement of the goals and objectives established at the time of project certification and financing approval.

Outcomes

Increase access and use of safe and sanitary wastewater collection services

Access to adequate wastewater treatment services

Reduction of untreated wastewater discharges to water bodies or others

Indicators

Actual (2014)

Increase number of new connections

429

Wastewater treatment capacity

0.13 MGD

Quantity of uncollected wastewater discharges eliminated

0.09 MGD

Outputs

 

Wastewater connections

429

Wastewater treatment plant

0.13 MGD

Wastewater collection lines

14.1 miles

Significant project finding(s)

The project improves wastewater collection and first-time wastewater treatment services and elimination of an estimated 0.09 MGD of untreated wastewater into shared transboundary surface water.